A couple weeks ago I had a pump and some pipe switched out on a water well. I wanted to bounce some numbers off yall and see if they seems in line.
5hp pump with controls $4,000
189' 2" galvanized pipe $1300
Labor $1250
The guy told me they always switch out the controls with the pump. Im not sure about that. That is the difference between $1500 and $4000.
The galvanized pipe would have cost $800 if I had gone to the store and bought it. I understand marking things up but to mark it up $500 on top of $1250 labor doesn't seem quite right.
Any thought? Is this pretty common? Im not mad at the guy but it seemed awefully high. He had done the same job twice already in years past and it was about 1/2 this bill. I didn't press him on a cost up front... my fault... but I want to know for next time.
Also as a reference, we drilled a brand new well with a 3hp about 100 yds from this one for $10k.
5hp pump with controls $4,000
189' 2" galvanized pipe $1300
Labor $1250
The guy told me they always switch out the controls with the pump. Im not sure about that. That is the difference between $1500 and $4000.
The galvanized pipe would have cost $800 if I had gone to the store and bought it. I understand marking things up but to mark it up $500 on top of $1250 labor doesn't seem quite right.
Any thought? Is this pretty common? Im not mad at the guy but it seemed awefully high. He had done the same job twice already in years past and it was about 1/2 this bill. I didn't press him on a cost up front... my fault... but I want to know for next time.
Also as a reference, we drilled a brand new well with a 3hp about 100 yds from this one for $10k.