Bridge replacement. Elements are:
1. Build a new bridge on temp pilings. Old bridge remains open to traffic.
2. Demolish old bridge in 5 days. Pilings have been reinforced and widened.
3. Slide the new bridge on to the old pilings. 5 days.
Website is http://www.miltonmadisonbridge.com/